Nikkiso to provide pumps for German LNG import terminal
What happened
Nikkiso CE&IG has been contracted to supply 16 submerged motor pumps for the Brunsbüttel LNG import terminal, a package awarded through the lead EPC, CS Gas North. The terminal is being built with two large LNG tanks and is scheduled to be operational in 2027, making this a real vendor mobilisation case tied to a firm EPC schedule. Watch whether the EPC tightens FAT, transport conditioning and acceptance windows as deliveries are scheduled
Why the category manager should care
Treat this as an execution case: contract award ties supplier commitments to the EPC schedule and reduces flexibility on delivery timing
Key facts
- Contract for 16 submerged motor pumps
- Project slated to be operational in 2027