LLOG selects Subsea7 for Who Dat East Gulf of Mexico project
What happened
LLOG awarded Subsea7 a contract to fabricate and install a 29‑km steel catenary riser and pipe‑in‑pipe, plus an umbilical and subsea controls, for the Who Dat East tieback in the US Gulf. Engineering is assigned to Houston and offshore activities are scheduled to begin in 2028 after the operator FID. This is operationally real for procurement because it creates clear long‑lead fabrication and installation demand to plan around; watch supplier sloting and mobilisation terms next
Why the category manager should care
Treat the award as a binding demand signal for specialist fabrication and installation capacity that should influence slot and contract negotiations now
Key facts
- 29‑km steel catenary riser and pipe‑in‑pipe scope
- Includes umbilical and subsea controls installation
- Offshore activities scheduled to start in 2028 following recent FID