WATCH: $12.5B gas project closing in on first LNG cargo as 10-storey module comes to Australia
What happened
Woodside confirmed delivery of the final and heaviest module for the Pluto LNG Train 1 upgrade to Karratha and moved to installation, hook-up and integration on site. The module is unusually large for the Pilbara and installation now shifts focus to heavy lifts, shore labour and tie-in sequencing. Watch contractor mobilisation windows, crane availability and how hook-up interfaces are assigned between EPC and client teams
Why the category manager should care
Treat the delivery as a real, binding installation window that should drive immediate mobilisation and contract clarity on heavy-lift and shore-labour scopes
Key facts
- Final module described as a 10-storey-high, very heavy lift delivered to site
- Fabrication spanned overseas yards with cross-border transport to Karratha
- Site work now moves to installation, hook-up and integration with Train 1