Newly drilled wells to boost eastern Australia gas supply before winter 2027
What happened
ExxonMobil and Woodside completed a five‑well drilling campaign (Turrum Phase 3) in the Gippsland Basin and the Valaris 107 rig has been demobilised. The development aims to use existing infrastructure to bring new gas into eastern Australia ahead of winter 2027, shifting activity from drilling to commissioning and tie‑ins. Watch whether the JV confirms firm commissioning dates and final marine support schedules
Why the category manager should care
Treat the campaign as a real, near‑term mobilisation signal: drilling is done and suppliers for tie‑ins, subsea controls and commissioning will be next to mobilise
Key facts
- Five new production wells drilled at Marlin B Complex
- Work completed from the Valaris 107 jack‑up rig
- Project designed to extend production using existing Gippsland infrastructure