WATCH: Allseas takes 17,200-ton North Sea giant ashore 42 years after first oil
What happened
Allseas used Pioneering Spirit to lift the 17,200-ton North Cormorant topsides ashore after a four-month offshore preparation campaign. The removal is the second topsides single-lift in a multi-year TAQA UK decommissioning program and shows heavy-lift vessel days are already allocated to large decommissioning jobs. Watch whether the programme's pace or additional single-lift work encroaches on global vessel availability that APAC projects might need
Why the category manager should care
Treat high-capacity vessel time as constrained capacity that can create mobilisation premiums; don’t assume local availability for heavy lifts
Key facts
- 17,200-ton topsides removed in a single-lift
- Four-month offshore preparation campaign preceded the lift
- Part of a multi-year TAQA UK decommissioning programme