DeepOcean concludes work for North Sea Teal West start-up
What happened
DeepOcean completed subsea construction, flowline and umbilical installations and commissioned the Teal West tieback to an FPSO. The campaign included a roughly three‑kilometre flowline and a diverless ROV‑executed high‑pressure flange tie‑in using proprietary tooling, making this an operational completion rather than a planning update. Watch whether follow‑on wells or extended commissioning drive additional short mobilisation windows for ROVs and spares
Why the category manager should care
Treat this as a live commissioning event that will pull on ROV resources, specialised tooling and short‑term spares rather than long‑lead fabrication slots
Key facts
- Subsea tieback to Anasuria FPSO via one producer well connected to about 3 km of flowline
- Scope included flexible production riser, flowline protection and umbilical installation
- Diverless ROV executed high‑pressure flange tie‑in with proprietary tooling