Wood secures contract for Dung Quat Refinery Upgrade and Expansion Project
What happened
Wood was awarded PMC services for the Dung Quat refinery upgrade and expansion, moving the programme from FEED into active project management. The scope includes procurement, engineering review and contract management ahead of commissioning scheduled in 2028, which makes vendor mobilisation, supervision and spare‑parts commitments operationally real. Watch how the PMC defines supplier approval gates and mobilisation windows; those decisions will shape procurement timing and commercial leverage
Why the category manager should care
Treat the award as a live procurement programme: confirm where the PMC owns vendor selection and which approvals remain with the buyer to avoid late-stage overruns
Key facts
- US$1.5 billion upgrade and expansion
- Commissioning scheduled to begin in 2028