Canada: Allseas to install critical subsea section of remote natural gas pipeline
What happened
Allseas won a contract to install about 50 km of concrete‑weight‑coated pipeline for the Prince Rupert Gas Transmission (PRGT) subsea section, linking an onshore system to a planned floating LNG facility. The work is scheduled for offshore installation in 2029 using large pipelay vessels and covers complex nearshore tasks including shore crossings, trenching and tie‑ins. Watch for the co‑developers’ final investment decision (FID) and supplier mobilization windows — they will determine when procurement needs to shift from planning to booking
Why the category manager should care
Treat PRGT as a real multi‑year mobilization signal and surface requirements for heavy‑lift pipelay vessels, shore logistics and permit support now
Key facts
- About 50 kilometers of 36‑ and 48‑inch concrete‑weight‑coated pipeline
- Installation activities scheduled for 2029 using Solitaire and Sandpiper
- Scope includes shore crossings, trenching, shore pull‑ins and tie‑ins