Delfin gives Siemens go-ahead for early works on second FLNG, as EIG’s MidOcean signs up to come aboard
What happened
Delfin issued a limited notice to proceed to Siemens Energy for long‑lead procurement on a second FLNG vessel, including SGT‑750 gas turbines and mixed‑refrigerant compressors. The LNTP is positioned as a pre‑FID milestone and supports a targeted final investment decision by year‑end, making these long‑lead items material to the project schedule. Watch whether the LNTP converts to a full notice to proceed and how suppliers set quote validity and deposit terms
Why the category manager should care
Treat the LNTP as an execution signal: secure delivery visibility, spare‑parts windows and reservation mechanics now rather than later
Key facts
- LNTP issued for long‑lead items including SGT‑750 gas turbines
- FLNG2 nameplate reported at 4.4 mtpa
- LNTP positioned as a pre‑FID milestone toward a year‑end FID