Weir to supply Brightstar’s Laverton gold crushing circuit
What happened
Weir secured a supply contract to deliver crushers, pumps and hydrocyclones and will support installation and commissioning for Brightstar Resources’ Laverton processing plant in Western Australia. The scope ties equipment delivery directly to on‑site installation responsibilities and supports a 1.5 million tonne per year processing facility with a target first production window cited by the project owner. This makes mobilisation sequencing, FAT and handover gates operationally important for buyers and their installation partners
Why the category manager should care
Treat this as a mobilisation and commissioning dependency: delivery is bundled with on‑site install work, so contracts must capture FAT, on‑site responsibilities and acceptance gates
Key facts
- Includes ENDURON ET jaw crusher and ENDURON EC cone crusher
- Supplies WARMAN pumps and CAVEX hydrocyclones
- Supports installation and commissioning of a 1.5 million tonne per year processing facility