Another local company comes onboard Indonesian natural gas project
What happened
Conrad Asia’s WNEL has awarded PT PAL an EPCT contract and a jack‑up has been contracted to drill six development wells on the Mako gas field. The work includes a ~59‑kilometre 18‑inch sales pipeline and mobilisation of the Admarine 502 jack‑up for the six‑well programme, making this a discrete regional mobilisation that reduces spare fleet windows. Watch whether follow‑on drilling and installation dates remain fixed or shift, which will change vessel competition for nearby P&A slots
Why the category manager should care
Treat this as an active demand event that reduces spare regional tonnage; early mobilisation clarity is necessary to avoid inflated pass‑throughs
Key facts
- Six development wells planned for the Mako gas field
- Approx. 59‑kilometre 18‑inch sales pipeline in scope
- Admarine 502 jack‑up assigned to the campaign