Jacket for EU’s largest offshore gas development sails away from Saipem’s shipyard
What happened
Saipem confirmed the jacket for the Neptun Deep gas development has sailed from its Sardinian yard to the Black Sea. The structure is among the largest built at the yard (about 7,500 tons, 135m tall with a 50x50m base) and will be lifted and installed offshore, tying into a 30‑inch, ~160km pipeline and fiber link. Watch supplier mobilization windows, crane/vessel bookings, and whether follow‑on subsea install dates firm up
Why the category manager should care
Treat the sail‑away as a hard execution date: suppliers will need booked vessels and crews, so confirm bookings and mobilization clauses now
Key facts
- 7,500‑ton jacket fabricated in Arbatax, Sardinia
- 135m tall jacket with 50x50m base
- 30‑inch pipeline ~160km plus fiber‑optic shore landing
- Project investment ~€4 billion; target first gas in 2027