Admarine 502 jackup contracted for Mako field drilling campaign offshore Indonesia
What happened
PT Pertamina and consortium contractors have awarded a firm contract for the Admarine 502 jackup to drill six development wells and install a conductor support frame for the Mako field. The award is a 180‑day firm contract with extension options and operations are expected to begin in Q2 2027, making mobilization timing and subsea tie‑back readiness operationally real. Watch whether pipeline tie‑in dates and MOPU readiness slip, which would affect contractor hold periods and spare staging
Why the category manager should care
Treat this as a binding demand signal for jackup capacity and MOPU support, not a tentative schedule, because the 180‑day firm contract fixes execution windows
Key facts
- 180‑day firm contract with extension options
- Six development wells and conductor support frame
- Operations expected to begin in Q2 2027